Council approves Ram’s Pointe homeownership plan and extension
The revised East Winston project retains $400,000 in city financing for 11 townhomes and two retail bays, with completion due by the end of 2029. The post Council approves Ram’s Pointe homeownership…
AI summary
The Winston-Salem City Council voted 8-0 on Nov. 2 to approve Ram's Pointe's revised housing plan, keep $400,000 in city financing and extend the completion deadline to Dec. 31, 2029. MTB3 Properties will replace a larger apartment-and-retail project at 310 Martin Luther King Jr. Drive with 11 for-sale townhomes and two retail bays, estimated at about $4.61 million. Two homes are reserved for households earning no more than 80% of area median family income. The General Government Committee had split 2-2, but all four members backed the plan at the full council. Members cited homeownership and business growth in East Winston. Hall cautioned that another extension might not get the same support, and Adams requested monthly reports on stalled city-supported projects. The city's assistance is a loan released in two installments tied to construction milestones and occupancy certificates. The developers attributed delays to soil remediation, engineering work and pandemic-related cost increases. The project connects to the East End Master Plan, which the council endorsed in 2018. Rezoning, which requires council approval after community engagement, remains a hurdle.
- Council voted 8-0 to approve 11 for-sale townhomes and two retail bays, retain $400,000 in city financing and extend the deadline to Dec. 31, 2029.
- Two homes are reserved for buyers earning up to 80% of area median income and may become income-restricted rentals if unsold six months after certificates of occupancy.
- The city loan will be released in two equal installments tied to construction milestones and certificates of occupancy; the staff report describes a 20-year, interest-only loan at 2%.
- The developers cited soil remediation, engineering work and pandemic-related construction cost increases as causes of delay, and said switching to homeownership was meant to keep the project viable.
- Rezoning still requires council approval after community engagement, and the developers are in talks with nearby property owners for overflow parking.