23-807: Authorize Supplemental Agreement No. 2 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway - Not to exceed $2,294,766.00, from $975,809.00 to $3,270,575.00 - Financing: City Hall, City Service, and Maintenance Facilities (2006 General Obligation Bond Fund) ($656,378.44), Park and Recreation Facilities (2006 General Obligation Bond Fund) ($486,636.56), Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund) ($289,187.80), and Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund) ($862,563.20 $1,151,751.00)
Dallas · 2023 · Introduced
Introduced March 13, 2023
Read the bill