26-356A: Authorize an increase in the construction services contract with BAR Constructors Inc. for additional work to include the installation of an alignment for the by-pass line, supportive work for the rehabilitation of two existing clarifier pipelines, critical repairs to the odor control pipeline at the Dallas headworks building, and the installation of a junction box and manholes to connect two existing pipelines associated with the Central Wastewater Treatment Plant Headworks and Primary Clarifiers Improvement Project - Not to exceed $1,421,849.94, from $50,432,956.25 to $51,854,806.19 - Financing: Wastewater Construction Fund *In alignment with Water and Wastewater Capital Improvement Program.
Dallas · 2025 · Introduced
Introduced December 3, 2025
Read the bill