SB 1384: Certificates of public convenience and necessity.
Latest action, March 4, 2026: Referred to Com. on RLS.
What this bill does
This bill would only change the wording of an existing rule, not its meaning. The rule says some utility companies must get approval first. They need that approval from the Public Utilities Commission before they build a new line or system. This approval is called a certificate of public convenience and necessity. It means the commission has agreed the new project is needed.
Official summary
Existing law prohibits gas corporations, electrical corporations, telegraph corporations, telephone corporations, water corporations, sewer system corporations, and certain railroad corporations from beginning construction of a street railroad, line, plant, or system without having first obtained from the Public Utilities Commission a certificate that the present or future public convenience and necessity requires or will require the construction, as specified. This bill would make a nonsubstantive change to that provision.