SB 1698: Modifies provisions relating to condemnation proceedings
Latest action, April 16, 2026: Second Read and Referred S Emerging Issues and Professional Registration Committee
Official summary
SB 1698 - This act modifies provisions relating to condemnation proceedings. Specifically, this act includes damages on the remaining or burdened property by the condemning authority's proposed use to be included in the determination of fair market value of a taking of less than the entire value of the property. Additionally, fair market value shall not include any increase in the value of the remaining or burdened property caused by the condemning authority's proposed use. This act also modifies the definition of "heritage value" by providing that such term means the value assigned to any real property that has been owned within the same family for at least twenty, rather than fifty, years. This act provides any corporation, political subdivision, state agency, cooperative, or person with the authority to condemn property shall give a 15-day notice to the property owner for purposes relating to surveying. Additionally, for easements acquired either by voluntary means or condemnation by corporations, political subdivisions, state agencies, cooperatives, or persons with the authority to condemn property, this act provides a 5-day notice requirement for entry and other duties related to abandonment or damages occurring to the property. Any such corporation, political subdivision, state agency, cooperative, or person that violates in any material respect the notice requirement or other duties shall be subject to a civil action by the property owner, the Attorney General, or prosecuting attorney for a civil penalty of up to $1,000 for each violation for each day, except that the maximum penalty shall not exceed $100,000 for all related violations, or for equitable relief. Upon the filing of a condemnation petition, a summons shall be issued giving a property owner at least 60 days, rather than 10 days, from the date of service of such petition before the petition may be heard. Additionally, this act provides that the property owner shall have 30 days from the date of service to answer such petition, except a failure to answer shall not constitute a default of the owner's rights to a hearing. At the initial hearing, the condemning authority shall have the burden to prove, by clear and convincing evidence, that there is statutory authority to condemn the property and that the empowering law, rules, and bylaws have been followed. This act also modifies just compensation for condemned property to include compensation equal to the amount of any taxes owed by a property owner as a consequence of the eminent domain proceeding. Additionally, for condemnations that result in a beginning farmer taking, the just compensation shall be an amount equivalent to the fair market value multiplied by 125% plus the amount of such taxes. This act defines a beginning farmer taking as any taking of any agricultural or horticultural property of a Missouri individual or entity that has not operated a farm or ranch for not more than 10 years and who participates in the operation of the farm or ranch. Additionally, the condemning authority shall include in the notice and written offer provided before the filing of a petition a statement that the property owner has the right to seek an award for heritage value, a homestead taking, or a beginning farmer taking, the right to seek attorney's fees if the amount awarded is greater than the offer, and a copy of the provision of this act regarding notices by and duties of the condemning authority and the list of obligations and remedies provided in such provision. This act also repeals the requirement that the electrical transmission line be designed to transmit electricity at 345-kilovolts or greater for determinations of good faith negotiations of condemnation of any agricultural or horticultural property for the construction of an electrical transmission line. For considerations of alternative locations, the written statement by the condemning authority to the owner on the reasoning for the rejection or acceptance of alternative locations shall be set forth with specificity, rather than by a brief statement. Additionally, any rejection of the landowner's suggested alternative location shall not be arbitrary or capricious nor induced by fraud, collusion, or bad faith, and shall be supported by substantial evidence. A condemning authority or the owner may seek a determination by the circuit court that these requirements have been met. Lastly, this act repeals the provision that any number of owners, residents in the same county or circuit, may be joined in one petition, except that the damages shall be separately assessed. This act is identical to SB 1699 (2026) and is similar to HB 3375 (2026). KATIE O'BRIEN
AI summary
SB 1698 changes the rules for condemnation proceedings, the process by which a government body, utility, or other entity with eminent domain power takes private property. It changes how fair market value is figured when only part of a property is taken: damage to the remaining property from the proposed use counts toward value, and any increase in value from that use does not. It shortens the family-ownership period needed to qualify for "heritage value" from 50 years to 20 years. Entities with condemnation power would have to give owners 15 days' notice before surveying and 5 days' notice before entering easements. They would also have other duties relating to abandonment of easements and damage to the property. Violations could bring civil penalties. The bill gives owners more time in court and makes the condemning authority prove its authority by clear and convincing evidence. Just compensation would also cover taxes the owner owes because of the taking. A higher payment is created for takings of land from beginning farmers. Condemning authorities would have to explain their reasons for rejecting or accepting alternative locations in more detail. The bill also drops the 345-kilovolt threshold in good-faith negotiation rules for electrical transmission lines on farmland. Finally, it repeals the provision allowing multiple owners to be joined in one petition.
- When less than the whole property is taken, fair market value includes damage to the remaining or burdened property from the proposed use, and excludes any increase in its value caused by that use.
- "Heritage value" applies to real property owned within the same family for at least 20 years, instead of 50 years.
- Condemning authorities must give owners 15 days' notice before surveying. For easements, whether acquired voluntarily or by condemnation, they must give 5 days' notice before entry, and they have other duties relating to abandonment and damage to the property.
- Material violations of these notice requirements or duties can lead to a civil action by the owner, the Attorney General, or a prosecuting attorney. Penalties are up to $1,000 per violation per day, capped at $100,000 for all related violations, or equitable relief.
- Owners get at least 60 days (instead of 10) after service of a condemnation petition before it can be heard. They have 30 days to answer, and failing to answer does not forfeit their right to a hearing.
- At the initial hearing, the condemning authority must prove by clear and convincing evidence that it has statutory authority to condemn and that it followed the governing law, rules, and bylaws.
- Just compensation includes the amount of any taxes the owner owes as a result of the eminent domain proceeding. For a "beginning farmer taking," compensation is 125% of fair market value plus those taxes.
- Before filing a petition, the condemning authority's notice and offer must tell owners of their right to seek awards for heritage value, a homestead taking, or a beginning farmer taking, and their right to attorney's fees if the award exceeds the offer. The notice must also include a copy of the notice-and-duties provision and the remedies it provides.
- Reasons for rejecting or accepting alternative locations must be stated with specificity. Rejection of an owner's suggested alternative must not be arbitrary, capricious, fraudulent, collusive, or in bad faith, and must be supported by substantial evidence. Either side may ask the circuit court to decide whether these requirements were met.
- Repeals the 345-kilovolt threshold in good-faith negotiation rules for transmission lines on agricultural or horticultural land, and repeals the provision allowing multiple owners to be joined in one petition.
- Owners of property subject to condemnation (eminent domain)
- Corporations, political subdivisions, state agencies, cooperatives, and persons with the power to condemn property
- Families who have owned real property for at least 20 years
- Beginning farmers and ranchers in Missouri whose agricultural or horticultural land is taken
- Utilities and developers of electrical transmission lines crossing agricultural or horticultural land
- Courts, the Attorney General, and prosecuting attorneys handling condemnation cases and enforcement
- Surveyors entering property for condemning authorities
The bill was first read in the Missouri Senate on February 23, 2026. It was second read and referred to the Senate Emerging Issues and Professional Registration Committee on April 16, 2026. It is now in committee. Usually the committee may hold a hearing and vote on whether to send the bill to the full Senate. Bills that are not acted on in committee typically do not advance.