2023-1106: Commission District(s): 1 and 6 CO-Change Order No. 2 to Contract No. 1238641 Scott Candler Water Treatment Plant - Ozone Generators Design and Installation: for use by The Department of Watershed Management (DWM). This contract consists of the design, installation, and the commission of two (2) ozone generators, including all supporting components, to operate in parallel with two existing generators. This request is to increase the contract term through September 30, 2024. Awarded to Heavy Constructors, Inc. CONTRACT TERM INCREASE ONLY.
Latest action, December 12, 2023: Approved — Board of Commissioners