2024-0735: Commission District(s): 3 and 7 CO - Change Order No. 17 to Contract No. 972548 Snapfinger Advanced Wastewater Treatment Facilities Expansion - Phase 2: for use by the Department of Watershed Management (DWM). This contract consists of the phase 2 expansion to the Snapfinger Advanced Wastewater Treatment Facility; inclusive of site preparation, modification of existing structures, and the construction of new structures. This request is to increase funding to allow for the completion of six (6) proposed changes. Awarded to Archer Western Construction, LLC. Amount not to exceed $509,486.83.

DeKalb County · 2024 · Introduced

Introduced June 4, 2024

Latest action, September 10, 2024: Approved — Board of Commissioners