2024-1342: Commission District(s): 2 and 6 CO - Change Order No. 2 to Contract No. 1296980 Scott Boulevard Phase III Watermain Replacement: for use by the Department of Watershed Management (DWM). This contract consists of the installation of 30-inch ductile iron pip (DIP) watermain and replacement of existing 6-inch distribution mains with 8-inch DIP inside the right-of-way and under existing pavement. This request is to increase the contract term through December 31, 2025. Awarded to Garney Companies, Inc. CONTRACT TERM INCREASE ONLY.
Latest action, December 10, 2024: Approved — Board of Commissioners