2024-1329: Commission District(s): District 3 and District 7 CO - Change Order No. 18 to Contract No. 972548 Snapfinger Advanced Wastewater Treatment Facilities Expansion - Phase 2: for use by the Department of Watershed Management (DWM). This contract consists of the phase 2 expansion to the Snapfinger Advanced Wastewater Treatment Facility; inclusive of site preparation, modification of existing structures, and the construction of new structures. This request is to increase the contract term through December 31, 2025. Awarded to Archer Western Construction, LLC. CONTRACT TERM INCREASE ONLY.

DeKalb County · 2024 · Introduced

Introduced October 16, 2024

Latest action, January 14, 2025: Approved — Board of Commissioners

Read the bill