HB 1151: Electric utilities; duty to furnish adequate service, high-demand customers.
Latest action, April 13, 2026: Approved by Governor-Chapter 745 (effective 7/1/2026)
What this bill does
This bill would let an electric utility wait before giving a customer power. The wait would be allowed to keep the power grid safe and steady. It would also apply when there is not enough power or room on power lines. A wait could also be used to follow rules for hooking big users to the grid. The change would start on July 1, 2027.
Official summary
Electric utilities; delay in provision of service permitted. Provides that a distributor of electric energy may delay the provision of service if such delay is necessary to maintain electric grid reliability, to avoid exceeding available generation or transmission capacity constraints, or to ensure compliance with load interconnection policies or rules issued by the State Corporation Commission or the Federal Energy Regulatory Commission. The bill has a delayed effective date of July 1, 2027. This bill is identical to SB 423.