050081: Authorizing the Director of Public Works to execute a construction manager at risk (CM@Risk) contract with M.A. Mortenson Company for the downtown arena project that includes Phase 1 Preconstruction Services in the amount of $390,000.00 and Phase 2 Construction Services in the amount of the total direct construction costs plus the CM@Risk’s general condition fee of $6,301,458.00 and the CM@Risk’s fee of 2.25% of the direct construction costs; authorizing the Director of Public Works to exercise the City’s option for Phase 2 construction services upon the City Council’s appropriation of funds from bond proceeds; finding it is in the best interests of the City to utilize the modified MBE/WBE solicitation procedures and requirements set forth in the CM@Risk contract documents and authorizing their use pursuant to section 38-91, Code of Ordinances.
Latest action, January 27, 2005: Passed — Council