S 4062: Establishes certain protections against demand by large-load addition customers in State.
Latest action, March 23, 2026: Introduced in the Senate, Referred to Senate Economic Growth Committee
What this bill does
This bill would keep some costs of very large new power users off other New Jersey customers. Big users add 50 megawatts or more at one connection point. If PJM, the grid operator, orders power cuts for such a user, the utility must cut only those big users. Costs of PJM's long-term power deals would also go to them. To get service, these users must post money as a guarantee and send detailed data to PJM.