14-0137: Request approval of Guaranteed Maximum Price (GMP) - Atlanta-Fulton Public Library System (AFPLS), RFP# 11RFP79559K-DJ, Alpharetta Library (L001) Construction Management-at-Risk Services in the amount of $10,363,145.04 with Moss & Associates, LLC (formerly P.R B.C., Inc.) to provide construction phase services for the new 25,000 sq. ft. Alpharetta Library. Effective upon the construction phase commencement date through substantial completion of work for *356 calendar days. (APPROVED) *THIS NUMBER WAS CHANGED TO 365. Vice Chair Darnell would like for the Purchasing Department to provide the names of the major sub-contractors to be used by the primary contractor on this contract. She would also like to know what percentage of women and minority owned companies are being utilized and a report analyzing this data.
Latest action, February 19, 2014: adopt — Board of Commissioners