14-0927: Request approval of a Guaranteed Maximum Price (GMP) - Atlanta-Fulton Public Library System (AFPLS), RFP #11RFP80690K-MH, Southeast Atlanta Library (L006) Construction Management-at-Risk Services in the amount of $5,799,240.98 with C. D. Moody Construction Company (Atlanta, GA) to provide construction phase services for the new 15,000 sq. ft. Southeast Atlanta Library. Effective upon the construction phase commencement date through substantial completion of work for 308 calendar days. (APPROVED)
Latest action, November 5, 2014: adopt — Board of Commissioners