S 3193: Requires electric public utilities to submit transmission project proposal to BPU for approval.
Latest action, January 28, 2026: Introduced in the Senate, Referred to Senate Economic Growth Committee
What this bill does
This bill would make electric companies in New Jersey get permission before building or changing a power line. The company would send a plan to the Board of Public Utilities. The plan would cover harm to nature and safety, all costs, and whether the line is needed. It would also list cheaper options. The board would have 90 days to check the plan. It would approve the plan if the plan makes sense, helps the public, and saves money.