A 4518: Requires electric public utilities to submit transmission project proposal to BPU for approval.
Latest action, March 9, 2026: Introduced, Referred to Assembly Telecommunications and Utilities Committee
What this bill does
This bill would make electric companies get approval before building or changing a power line. The company would send a plan to the state Board of Public Utilities. The plan must cover effects on nature, scenic places, historic sites, and safety. It must also list all costs. It must show the project is needed and name cheaper options. The board would have 90 days to decide if the plan is fair, good for the public, and worth the cost.