050724: Approving a $3,362,017.00 contract with Kraus-Anderson Construction for Auditorium Plaza Garage; authorizing a $102,445.00 third amendment with Structural Engineering Associates, Inc. for additional design of vendor area and parking control equipment, special inspection services and construction observation; reducing appropriations in the amount of $300,000.00 in the Convention Center Garages Fund; appropriating it to the Garage Improvements account of the Convention Center Garages Fund; authorizing the Director of Public Works to expend $4,171,463.00, including contingencies, for the project; appropriating $39,960.00 to the Public Art Fund; declaring the City’s intent to reimburse itself for certain expenditures; and designating requisitioning authority.
Latest action, June 16, 2005: Passed as Substituted — Council