22-0615: Request approval of a change order less than 10% - Department of Public Works, 20ITB126798K-JAJ, ARFF Phase II with Trident Building Solutions LLC, Atlanta, GA. in an amount not to exceed $101,717.58, including owner’s contingency, for additional plumbing, drainage, footings, and slab fill and to amend the corresponding contract specifications and contract duration by 45 days. Effective upon BOC approval. (APPROVED UPON ADOPTION OF THE CONSENT AGENDA)

Fulton County · 2022 · Introduced

Introduced June 22, 2022