Civicly

25-0570: Request approval of Guaranteed Maximum Price (GMP) - Department Public Works, 23RFP139070K-JAJ, Progressive Design-Build Services for Campbellton Road Pump Station and Force Main in an amount not to exceed $20,332,906.00 with Sol Construction, LLC (Atlanta, GA), to perform all final design and construction activities associated with the installation of a new pump station and associated force main pipelines to serve South Fulton County. Effective upon issuance of the Notice to Proceed (NTP) with work to be completed within 24 months of the issuance of the NTP. (APPROVED)

Fulton County · 2025 · Passed

Introduced June 18, 2025

Latest action, August 6, 2025: approve — Board of Commissioners

Read the bill